Hardware Team Completes Its Work

Project Sammaan has reached a crossroads of sorts now that all of the requisite approvals for construction are in place and NBCC has been brought on board as the contractor for all facilities in both Bhubaneswar and Cuttack; it is time for the hardware team, led by Quicksand, to scale back their involvement and allow the software team, led by J-PAL, to complete the remaining work necessary prior to opening the facilities in the host communities.

Any regular reader of this blog will know that it has been a long, arduous process getting to this point. Project Sammaan has been an exercise in patience and perseverance, and an undertaking that has taught us a great many things over the (more…)

Viewing Behavior Change Through Another Lens

As is well known and well covered in the media, there is a sanitation crisis in India, with over half the population (roughly 600 million people) forced to open-defecate every day due to a lack of adequate facilities, infrastructure, and even a basic understanding of the importance of healthy sanitation habits. This makes India the world’s biggest culprit in terms of open-defecation, with more than double the amount of the next 11 countries combined.

Additionally, the country loses over US$50 billion dollars per year (roughly 6% of GDP) due to sanitation-related illnesses, one child under the age of 5 dies every 20-seconds from diarrhea stemming from water-borne illnesses, safety of women and girls remains one of the primary concerns in settings where they are forced into the (more…)

Financial Considerations

Project Sammaan remains a tale of two cities, with construction related activities continuing at a feverish pace for the Community Toilet facilities in Cuttack whereas matters for the same facility type in Bhubaneswar remaining stalled as we continue waiting for the Administrative Approval to be granted by the H&UD Department. Only once this approval is granted can the contracts with NBCC be signed, and the pre-construction activities commence.

Over the past few days, there has been some cause for optimism in regards to Bhubaneswar’s Community Toilets: the file has moved from the Finance (more…)

Construction Timelines & Cause for Concern

News that National Buildings Construction Corporation (NBCC) has been identified as the contractor for all of the Project Sammaan facilities in both Bhubaneswar and Cuttack brought with it both an incredible sense of relief and a torrent of new work to accomplish all of the project’s required pre-construction activities prior to breaking ground on the first facilities.

I have written briefly in the past about these pre-construction efforts, but now that we have a contractor on-board we have shifted into the day-to-day planning that will be required to effectively, efficiently, and successfully pull off the construction of the 79 separate facilities in the initial phase of Project Sammaan. With all of the different organizations involved, and each with their own sets of needs and related challenges, the logistics of coordinating all individual efforts such that the collective goal of getting the facilities online as quickly as possible is (more…)

The Waiting Game Continues

For over four months now, the project team has found itself in a state of limbo awaiting a decision by the Housing and Urban Development Department (H&UD) in Bhubaneswar on whether or not the contracts for constructing the Sammaan facilities can be awarded to a Public Sector Unit (PSU) on a nomination basis. And that waiting game continues unabated.

There have been several posts written on this blog during this time attempting to convey any information possible, though much of this was speculatory and emotive: we simply haven’t had anything concrete to report leaving us in a position to simply share our feelings as project activities (more…)

A Need for Clarity & Access

The possibility of a Public Sector Unit (PSU) being awarded the contracts for constructing the Sammaan facilities on a nomination basis was greeted with great excitement, support, and an overwhelming sense of relief; after a year-and-a-half of false starts and setbacks, it was beginning to look like the tendering process was finally over. That positive outlook has been tempered quite a bit over the past two months as the decision on a PSU’s nomination remains pending, leaving the team in an extended state of limbo and uncertain as to what steps can be taken to expedite the review.

Much of this uncertainty lies in the lack of clarity regarding what is entailed in the review process currently under way with various representatives at the H&UD, Finance, and Public Health Departments. We simply don’t know what the protocols are, who is responsible for each step, and what the timelines associated with each are. Ultimately, the team finds itself in a position of having to be reactive, to wait for requests from the various (more…)

The Waiting Game

Project Sammaan is currently in a state of limbo with decisions still pending on nominating a contractor to construct the facilities in both Bhubaneswar and Cuttack. After several failed attempts at publicly tendering the facility construction, reports were issued by both the BMC and CMC to senior officials at the Housing & Urban Development Department supporting the nomination of a Public Sector Unit (PSU) as contractor.

The decision to nominate a PSU received the full support of the project team and, since late July, the reports have been subject to review by various members of the H&UD, Public Health, and (more…)

Pre-Construction Activities

There are a series of interrelated activities that must occur prior to the commencement of construction on the Sammaan facilities in order to ensure the project is as effective as possible. The challenge is that these activities cannot begin until after the contractors have been selected and a clearly defined construction timeline created as they need to be completed as close to the commencement of building the facilities as can be afforded.

Naturally, the extensive delays in the tendering process and, ultimately, in finding suitable contractors for facility construction has put the timelines for the pre-construction activities in a (more…)

Light at the End of the Tunnel?

As any regular reader of this blog will attest, tendering for construction of the Sammaan facilities has been a singular focal point of, and considerable challenge for, Project Sammaan for nearly a year-and-a-half. The hurdles have been well documented, as have the associated peaks and valleys of emotions with each perceived success and setback. It is with this history in mind that we share, with caution, potentially great news that could finally lead to ground-breaking on the first Sammaan facilities.

To provide some background first, the third reissue of the tender (this time split into four individual packages) in Cuttack once again did not yield any interested bidders, let alone qualified ones. In Bhubaneswar, based on the decision to reduce the number of sites for the initial phase of tendering (more…)

Revisiting Bhubaneswar’s Sites

The drastically reduced budget for the Community Toilets in Bhubaneswar will only allow us to build only 26 of the originally planned 60 facilities. This meant that the team had to decide which communities would receive a facility and which would be forced to keep their fingers-crossed in hopes that sometime in the future their needs will be met. Doing so was no small task, and one that required the participation of virtually all those working on the initiative. Further complicating matters was the two-week deadline mandated by the government to complete the work.

The first step in this process was visiting all proposed sites to identify any encroachment issues. As the land was identified and allocated to the project nearly 2 years ago, there was serious concern that many of the sites would no longer be open and available for construction. In fact, (more…)