As is well known and well covered in the media, there is a sanitation crisis in India, with over half the population (roughly 600 million people) forced to open-defecate every day due to a lack of adequate facilities, infrastructure, and even a basic understanding of the importance of healthy sanitation habits. This makes India the world’s biggest culprit in terms of open-defecation, with more than double the amount of the next 11 countries combined.

Additionally, the country loses over US$50 billion dollars per year (roughly 6% of GDP) due to sanitation-related illnesses, one child under the age of 5 dies every 20-seconds from diarrhea stemming from water-borne illnesses, safety of women and girls remains one of the primary concerns in settings where they are forced into the (more…)

Construction Timelines & Cause for Concern

News that National Buildings Construction Corporation (NBCC) has been identified as the contractor for all of the Project Sammaan facilities in both Bhubaneswar and Cuttack brought with it both an incredible sense of relief and a torrent of new work to accomplish all of the project’s required pre-construction activities prior to breaking ground on the first facilities.

I have written briefly in the past about these pre-construction efforts, but now that we have a contractor on-board we have shifted into the day-to-day planning that will be required to effectively, efficiently, and successfully pull off the construction of the 79 separate facilities in the initial phase of Project Sammaan. With all of the different organizations involved, and each with their own sets of needs and related challenges, the logistics of coordinating all individual efforts such that the collective goal of getting the facilities online as quickly as possible is (more…)

The Waiting Game Continues

For over four months now, the project team has found itself in a state of limbo awaiting a decision by the Housing and Urban Development Department (H&UD) in Bhubaneswar on whether or not the contracts for constructing the Sammaan facilities can be awarded to a Public Sector Unit (PSU) on a nomination basis. And that waiting game continues unabated.

There have been several posts written on this blog during this time attempting to convey any information possible, though much of this was speculatory and emotive: we simply haven’t had anything concrete to report leaving us in a position to simply share our feelings as project activities (more…)

Institutional Knowledge

Any long-term engagement requires a certain level of institutional knowledge in order to be sustainable and ever forward-moving. This becomes especially poignant the longer and more complex the initiative. Given Project Sammaan’s scope and long-term focus, this level of understanding is simply not an option, but rather an absolute must if we are to be successful.

There are many ways in which the project is structured to ensure that the decisions made that define the project are documented as they happen, and this information is disseminated to project partners or in the very least made readily available. Communications efforts span from (more…)

The Waiting Game

Project Sammaan is currently in a state of limbo with decisions still pending on nominating a contractor to construct the facilities in both Bhubaneswar and Cuttack. After several failed attempts at publicly tendering the facility construction, reports were issued by both the BMC and CMC to senior officials at the Housing & Urban Development Department supporting the nomination of a Public Sector Unit (PSU) as contractor.

The decision to nominate a PSU received the full support of the project team and, since late July, the reports have been subject to review by various members of the H&UD, Public Health, and (more…)

Pre-Construction Activities

There are a series of interrelated activities that must occur prior to the commencement of construction on the Sammaan facilities in order to ensure the project is as effective as possible. The challenge is that these activities cannot begin until after the contractors have been selected and a clearly defined construction timeline created as they need to be completed as close to the commencement of building the facilities as can be afforded.

Naturally, the extensive delays in the tendering process and, ultimately, in finding suitable contractors for facility construction has put the timelines for the pre-construction activities in a (more…)

Light at the End of the Tunnel?

As any regular reader of this blog will attest, tendering for construction of the Sammaan facilities has been a singular focal point of, and considerable challenge for, Project Sammaan for nearly a year-and-a-half. The hurdles have been well documented, as have the associated peaks and valleys of emotions with each perceived success and setback. It is with this history in mind that we share, with caution, potentially great news that could finally lead to ground-breaking on the first Sammaan facilities.

To provide some background first, the third reissue of the tender (this time split into four individual packages) in Cuttack once again did not yield any interested bidders, let alone qualified ones. In Bhubaneswar, based on the decision to reduce the number of sites for the initial phase of tendering (more…)

Progress Report & Looking Ahead

Over the course of the past several weeks, the project management team has launched a bit of a letter-writing campaign to our partners at the municipal corporations, as well as various other senior members of the Odisha state government. The purpose of these formal correspondences is to ensure that the challenges and opinions of the non-government partners working on Project Sammaan are taken into consideration and, more importantly, become part of the permanent record for the initiative.

It can be extremely challenging navigating the bureaucracy of the municipal corporations especially when seeking to ensure that all pertinent information is communicated to all necessary parties in a timely and efficient manner. Emails are ineffective as some of the government partners lack regular access to computers and, further to that point, few have personal email addresses, making it difficult to know if messages sent to generic, catch-all (more…)

Sammaan is looking for a Project Manager

We will soon be hiring a Project Management Company to overlook construction. We are thus looking for an experienced Project Manager to manage their efforts, to represent the project consortium to the government and to oversee the project overall. Please find below a detailed job description for the same, along with job requirements and eligibility criteria.

Project Sammaan_Project Manager_Job Description_4 June

Letters, Meetings, and a Whole Lot of Patience

Maintaining a website and a as-real-time-as-possible blog for Project Sammaan has been extremely challenging for several reasons. The most basic challenge is simply getting people from the various organizations working on the project to contribute. This is certainly understandable, to a certain degree, considering that many of these people have no background, or even interest, in writing. The problem inherent in this recalcitrance though is the mandate to capture the Project Sammaan experience for inclusion in the end-deliverable of a toolkit that will help guide the efforts of others interested in replicating the project. After all, only you can share your story; no one else can know or adequately capture what your experience has been like.

This is well and truly an ancillary concern though, and one that we’ve taken great strides in addressing through various strategies, whether it be creating questionnaires for people to fill out and then work with me to structure the answers into some cogent and coherent narrative or simply me chasing after and threatening people to get them to contribute. The real issue (more…)