Revisiting Bhubaneswar’s Sites
The drastically reduced budget for the Community Toilets in Bhubaneswar will only allow us to build only 26 of the originally planned 60 facilities. This meant that the team had to decide which communities would receive a facility and which would be forced to keep their fingers-crossed in hopes that sometime in the future their needs will be met. Doing so was no small task, and one that required the participation of virtually all those working on the initiative. Further complicating matters was the two-week deadline mandated by the government to complete the work.